Legislature Enacts Statute of Limitations for State

Monday, August 21, 2017

In a first step to curbing the unlimited enforcement powers of the State, the New Hampshire legislature has passed a law that will provide a three-year statute of limitations for the State when pursuing any personal or civil enforcement action. The new law becomes effective on January 1, 2018. Prior to the enactment of this law, the New Hampshire Supreme Court had concluded  in State v. Lake Winnipesaukee Resort, LLC, 159 N.H. 42, 45 (2009) – that the State had no time limit to pursuing an enforcement action under the centuries old common law doctrine of nullum tempus.

Late last year, in a case handled by Preti Flaherty attorneys Ken Rubinstein and Nathan Fennessy, the New Hampshire Supreme Court revisited the scope of nullum tempus in City of Rochester v. Marcel A. Payeur, Inc. et al. Case No. 2016-0212 (N.H. Dec. 13, 2016), finding that the doctrine did not apply in the context of a breach of contract action brought by a municipality. In reaching its decision in City of Rochester, the court showed skepticism toward the idea that the State, when acting as a private participant in the market, would enjoy the benefits of the doctrine in pursuing a breach of contract action.

Shortly after the decision in City of Rochester, the New Hampshire legislature took up the issue in the legislative session. The new law establishes that the State may not wait more than three years after obtaining “actual knowledge” of the wrongful conduct before pursuing an enforcement action or civil action unless the State “demonstrates the delay was not unreasonable or prejudicial to the defendant, or that the detriment to the public caused by the delay outweighs the detriment to defendant.” The law also provides that the “limitation shall not apply to any violation or wrong that is ongoing or has otherwise not been corrected.” Although the exceptions contained in the new law could swallow the rule, the enactment of a statute of limitation is a good first step to providing contractors with degree of certainty when their potential liability on a State project will end.

Active Negligence May Not Preclude General Contractor from Enforcing Contractual Indemnification

Wednesday, May 17, 2017

Some statesthough generally not in the Northeastpreclude a general contractor from recovering under a contractual indemnification provision against a subcontractor if the claim is the result, in any way, of active negligence or willful misconduct on the part of the general contractor. A recent decision by an appellate court in California, Oltmans Construction co. v. Bayside Interiors, Inc. Case No. A147313 (Cal. App. 1st Dist. March 30, 2017), however, shows that courts are increasingly skeptical of such broad interpretations of anti-indemnity statutes that preclude general contractors from pursuing their bargained-for contractual indemnification rights. Under Oltmans, a general contractor will just have to show that the injury or damage was not solely caused by its active negligence, and might have been caused in part by others, to maintain a contractual indemnification claim against its subcontractor.

The case arose from a jobsite injury suffered by an employee of a sub-subcontractor on the project. The injured party sued the general contractor and the property owner. The general contractor then sued the subcontractor alleging a right to express contractual indemnity. The general contractor argued that, even if it was actively negligent, it was still entitled to be indemnified for the portion of any liability incurred as a result of the negligence of others.

The trial court rejected the general contractor’s argument, but the appellate court agreed with the general contractor and concluded that the trial court had erred in granting summary judgment to the subcontractor. The appellate court found that denying the general contractor indemnification for the portion of any liability it may incur attributable to the fault of the sub-subcontractor, the employee, or others would be inconsistent with the language of the contractual indemnity provision and the purpose of the indemnification statute. The appellate court focused on the fact that there was no evidence that the injury was caused solely by the actions of the general contractor. The general contractor was therefore entitled to pursue its indemnification claim for that portion of any liability that was not result of the general contractor’s active negligence.

Third Circuit Rules That Filing of Mechanic’s Lien Violates Bankruptcy Stay

Tuesday, May 9, 2017

In a decision that will impact how subcontractors deal with an insolvent general contractor, the Third Circuit in In re Linear ElectricCompany, Inc., Case No. 16-1477, ruled that a subcontractor creditor violated the automatic stay imposed by a general contractor’s bankruptcy filing when, post-bankruptcy, the subcontractor filed a mechanic’s lien against the owner of the construction project. Much like New Hampshire’s statutory system, New Jersey’s construction lien statute allows subcontractors and suppliers to lien an owner’s property to the extent of any unpaid balance that remains due and owing to the general contractor under their contract.  

In this case, the subcontractor claimed that it did not violate the stay, because it had filed its lien only against property of the owner, not property of the general contractor. The Third Circuit, however, disagreed. Because the subcontractor could only assert the lien against the owner to the extent any money remained owing to the general contractor, the Circuit found the lien violated the stay by preventing the owner from paying over the money it owed to the general contractor’s bankruptcy estate. In other words, the mechanic’s lien had effectively attached the bankrupt general contractor’s receivable, which is prohibited under Section 362 of the Bankruptcy Code.

This is another reminder for subcontractors and suppliers that they may need to exercise their lien rights earlier in the process to preserve those rights. Delay in pursuing unpaid invoices could deprive them of the benefit of a statutory lien against the project.

Gregory Moffett from Preti Flaherty's Bankruptcy, Creditor’s Rights and Business Restructuring Practice Group contributed to this blog.     

Boston Public School Master Plan Calls Construction Industry to Action

Monday, April 10, 2017

In March, Boston mayor Marty Walsh announced that the city is introducing a “new era of school investment,” a $1 billion, 10-year master plan called BuildBPS. Developed with planning firm Symmes Maini & McKee Associates, BuildBPS represents a major business opportunity for the local construction industry to play a part in shaping the future of Boston’s public schools.

Modernizing the Classrooms

A 2016 survey found that 60 percent of students, parents, and staff rated the condition of Boston’s public schools as “fair” or “poor.” More than 50 percent of Boston’s 127 public schools were built before World War II, and less than half of the buildings have been fully renovated. Through BuildBPS, the city plans to build modern classrooms with energy efficient environments, allowing for more fresh air and natural sunlight, and technology to promote 21st century learning and teaching methodologies.

Project Funding

Primary capital spending for BuildBPS will be funded by bonds issued by the City, with secondary funding through matching funds from the Massachusetts School Building Authority. Funding for the highest-priority projects is expected to be included in the proposal for Boston’s 2018 capital budget.

The Preti Flaherty Construction Law group is keeping abreast of this topic and will provide updates as it develops. Contact us with any questions or comments.