The Massachusetts Supreme Judicial Court issued a very significant ruling yesterday regarding the use of the CM-At Risk delivery method, particularly on public jobs.
In Coghlin Electrical Contractors, Inc. v. Gilbane Building Company, the Court held that a construction manager who performed preconstruction services to assist in the development of plans and specifications did not waive the owner’s implied warranty as to the sufficiency of the plans and specifications. In addition, the Court held that the contract’s language requiring the construction manager to indemnify the owner from any subcontractor claims did not bar the construction manager from suing the owner – even to pass along a subcontractor’s claim – for a claim based upon errors in the plans and specifications.
The Massachusetts Division of Capital Asset Management and Maintenance (“DCAM”) entered into a contract with Ellenzweig Associates to prepare designs to build a psychiatric facility at the site of the Worcester State Hospital (“Project”).
When the designs were partially completed, DCAM entered into a contract with Gilbane Building Company (“Gilbane”) as the CMAR. Gilbane then entered into a subcontract with Coghlin Electrical Contractors, Inc. (“Coghlin”), to perform electrical work. The subcontract incorporated by reference the terms of the contract between DCAM and Gilbane. A dispute arose between Coghlin and Gilbane regarding additional costs that Coghlin alleged resulted from various scheduling, coordination, management, and design errors. After Coghlin filed suit against Gilbane, Gilbane filed a third-party complaint against DCAM, asserting that, "in the event that Coghlin proves its claims against Gilbane," DCAM committed a breach of its contract with Gilbane by refusing to pay Gilbane the amounts claimed by Coghlin. DCAM filed a motion to dismiss the third party complaint claiming that Gilbane could not obtain indemnification for design defects when Gilbane had participated in the development of plans and specifications for the Project.
The Massachusetts Superior Court had originally held that a Construction Manager who provides design assist services could not make a claim against the owner when later problems arise on the job due to defects in the plans and specs. That lower court held that although Massachusetts recognizes the “Spearin Doctrine,” in which the project owner gives an implied warranty regarding the feasibility of the designer’s plans and specs, the CM could not raise that warranty, given their role in developing the plans and specs. The Court also held that the contract’s indemnification language (which required the construction manager to indemnify the owner from subcontractor claims) constituted a further waiver in this case, since the dispute originated with a subcontractor’s complaint regarding the plans and specs.
The reversed the lower court’s decision, holding:
“(1) under our common law, a public owner of a construction management at risk project gives an implied warranty regarding the designer's plans and specifications, but the scope of liability arising from that implied warranty is more limited than in a design-bid-build project; (2) the construction management at risk contract in this case did not disclaim the implied warranty; and (3) the indemnification provision in the contract did not prohibit the CMAR from filing a third-party complaint against the owner that sought reimbursement under the implied warranty for damages claimed by the subcontractor arising from the insufficiency of or defects in the design.”
The SJC reached its decision in part based on the fact that “t]he possibility that the CMAR may consult regarding the building design does not suggest that the CMAR should be the guarantor against all design defects, even those that a reasonable CMAR would not have been able to detect.” The SJC found that the scope of the implied warranty will depend upon whether the CMAR “acted in good faith reliance on the design and acted reasonably in light of the CMAR's own design responsibilities.” In making such determinations, courts will need to consider the “CMAR's level of participation in the design phase of the project and the extent to which the contract delegates design responsibility to the CMAR.” The SJC signaled that “[t]he greater the CMAR's design responsibilities in the contract, the greater the CMAR's burden will be to show, when it seeks to establish the owner's liability under the implied warranty, that its reliance on the defective design was both reasonable and in good faith.”
This is a significant decision because the lower court’s ruling, if upheld, would have a chilling effect on construction using the CM-At Risk method as builders would be far more hesitant to provide design assist services, if they thought that doing so would make them responsible for the entire design.
For further information, please contact Ken Rubinstein at 617.226.3868 / krubinstein@preti.com; or Nathan Fennessy at 603.410.1528 / nfennessy@preti.com.
Principal May Not Be Held Liable Under “Joint Action” Theory for Breach of Contract By Company, But May Have Individual Liability for Unfair or Deceptive Trade Practices
Thursday, August 6, 2015
The Connecticut Supreme Court recently issued an opinion in Joseph General Contracting, Inc. v. Couto, (SC 19209) that preserved the limited liability of a principal for breach of contract claims against the company, but opened the door to individual liability for principals for unfair or deceptive trade practice act violations. The Connecticut Supreme Court reversed the trial court and first level appellate court decisions finding that the principal of a company could be held liable for breach of contract under a “joint action” theory with his companies. In a somewhat unprecedented action, the Connecticut Supreme Court rejected the factual findings of the trial court and concluded that there was no “blurring” of the distinction between corporate and personal liability for the original construction contract. It held that the trial court (and appellate court) improperly looked to other agreements to draw such a conclusion. Finding that the subsequent agreements between the principals and plaintiffs clearly distinguished between the principal’s personal obligations and the construction contract with the principal’s company, the court found no basis for imposing personal liability for breach of the construction contract.
On the other hand, the Connecticut Supreme Court found that the principal could be held personally liable under Connecticut’s version of the unfair trade practices act. The court adopted the test employed by federal courts in construing the Federal Trade Commission Act that an individual may be held liable for an entity’s violation of the unfair trade practices act if the individual “either participated directly in the entity’s deceptive or unfair acts or practices, or that he or she had the authority to control them.” It then concluded that “[a]n individual’s status as controlling shareholder or officer in a closely held corporation creates a presumption of the ability to control.” Since the principal in Joseph General was the sole shareholder exercising control over the company, the court concluded that he could be held personally liable.
On the other hand, the Connecticut Supreme Court found that the principal could be held personally liable under Connecticut’s version of the unfair trade practices act. The court adopted the test employed by federal courts in construing the Federal Trade Commission Act that an individual may be held liable for an entity’s violation of the unfair trade practices act if the individual “either participated directly in the entity’s deceptive or unfair acts or practices, or that he or she had the authority to control them.” It then concluded that “[a]n individual’s status as controlling shareholder or officer in a closely held corporation creates a presumption of the ability to control.” Since the principal in Joseph General was the sole shareholder exercising control over the company, the court concluded that he could be held personally liable.
New American Arbitration Association Construction Industry Arbitration Rules in Effect July 1
Tuesday, June 30, 2015
The American Arbitration Association has issued revised
Construction Industry Rules and Mediation Procedures, which are intended to
provide “a more streamlined, cost-effective and
tightly managed process.” Some of the most significant amendments
include:
- A mediation step
for all cases with claims of $100,000 or more (with both parties having
the ability to opt out).
- Consolidation and joinder time frames and filing
requirements to streamline these
increasingly involved issues in construction arbitrations.
- New preliminary hearing rules to provide more structure and organization to get the
arbitration process on the right track from the beginning.
- Information exchange measures to give arbitrators a greater degree of control to
limit the exchange of information, including electronic documents.
- Availability of emergency measures of protection in contracts that have been entered into on or after
July 1, 2015.
- Enforcement power of the arbitrator to issue orders to parties that refuse to comply with
the Rules or the arbitrator’s orders.
- Permissibility of dispositive motions to dispose of all or part of a claim or to narrow the
issue in a claim.
State May Not Disclose Trade Secrets Submitted as Part of RFP Response
Friday, May 15, 2015
If
you have ever agonized about whether to include certain confidential business
information in a bid for a state contract in New Hampshire because of concerns
that your competitors might get their hands on it, you should find some comfort
in the New Hampshire Supreme Court’s recent decision in CaremarkPCS Health, LLC v. New Hampshire Department of Administrative Services, No. 2014-120. In
2010, the Department issued a Request for Proposals (RFP) for pharmacy benefit
management services for the State of New Hampshire’s health plan.
Caremark submitted a bid and ultimately obtained a contract with the
State to perform the work.
In
2011, the Department received multiple requests to inspect and copy Caremark’s
bid and the final contract. Two of the requests were made by Caremark’s
competitors. Caremark, after being informed by the Department of the requests,
responded that certain confidential information contained in the bid and final
contract was exempt from disclosure under the Right-to-Know Law. The Department
and Caremark disputed whether certain information was subject to
disclosure. When the parties failed to resolve the dispute, Caremark
filed a petition for declaratory and injunctive relief seeking to enjoin the
Department from disclosing certain information.
Project Management Firm Not Liable for Subcontractor’s Injuries
The Suffolk
(MA) Superior Court, in Rodrigues, et al.
v. Tribeca Builders Corp., et al. (Civil Action No. 13-00730-C), recently
granted summary judgment to a project management firm retained by a property’s
landlord/owner, who was sued after the Plaintiff was injured at a construction
site. The Plaintiff was injured when a
handicap chair-lift he was helping to move at the construction site fell on
him. The Plaintiff was employed by a
subcontractor hired by the general contractor.
The Plaintiff brought claims against the general contractor, another
subcontractor, and the project management firm hired by the landlord to provide
project management services on its behalf.
The Court held that the project management firm owed no duty to the Plaintiff, and thus the Plaintiff could not assert a negligence claim against it. In reviewing the contract between the landlord and project management firm, the Court found that the project management firm was to carry out a variety of logistical, managerial and administrative functions related to the construction, most of which involved monitoring the project’s adherence to its agreed budget and schedule. The Court described the firm’s role as that of a conventional “Clerk of the Works,” functioning as they eyes and ears of the owner in respect to the administration of the project. Nothing in the contract between the owner/landlord and the project management firm remotely suggested that the firm’s administrative functions extended in any way to matters of construction safety. The Court also noted that the firm had no contractual relationship with the Plaintiff, the general contractor, or any subcontractors.
The Court also pointed out that even if the project management firm could somehow be deemed to owe a duty of care to the Plaintiff, the undisputed evidence was clear that the firm had nothing at all to do with the accident that injured Plaintiff. The firm did not attend or participate in safety meetings, did not direct or instruct anyone regarding how their work should be performed, and had no knowledge of, involvement in, or communications regarding the handicap chair-lift that injured the Plaintiff, or the equipment used to move it.
In sum, the Court noted that while the project management firm played a significant administrative role in coordinating the scheduling and other logistical aspects of the construction project, there is no evidence that it was in “control” of the job-site, directed the work of any subcontractors, or had any connection whatsoever to the operations or movement of the chair-lift that caused the Plaintiff’s injury.
The Court held that the project management firm owed no duty to the Plaintiff, and thus the Plaintiff could not assert a negligence claim against it. In reviewing the contract between the landlord and project management firm, the Court found that the project management firm was to carry out a variety of logistical, managerial and administrative functions related to the construction, most of which involved monitoring the project’s adherence to its agreed budget and schedule. The Court described the firm’s role as that of a conventional “Clerk of the Works,” functioning as they eyes and ears of the owner in respect to the administration of the project. Nothing in the contract between the owner/landlord and the project management firm remotely suggested that the firm’s administrative functions extended in any way to matters of construction safety. The Court also noted that the firm had no contractual relationship with the Plaintiff, the general contractor, or any subcontractors.
The Court also pointed out that even if the project management firm could somehow be deemed to owe a duty of care to the Plaintiff, the undisputed evidence was clear that the firm had nothing at all to do with the accident that injured Plaintiff. The firm did not attend or participate in safety meetings, did not direct or instruct anyone regarding how their work should be performed, and had no knowledge of, involvement in, or communications regarding the handicap chair-lift that injured the Plaintiff, or the equipment used to move it.
In sum, the Court noted that while the project management firm played a significant administrative role in coordinating the scheduling and other logistical aspects of the construction project, there is no evidence that it was in “control” of the job-site, directed the work of any subcontractors, or had any connection whatsoever to the operations or movement of the chair-lift that caused the Plaintiff’s injury.
Labels:
accident,
construction contract,
contractor,
Court,
defendant,
handicap,
injury,
landlord,
plaintiff,
project management,
Suffolk Superior Court
Preti Attorneys Secure Significant Win for NH Construction Industry – NH Superior Court Rejects Bid to Expand Scope of Nullum Tempus
Wednesday, April 15, 2015
In City of Rochester v. Marcel A. Payeur, Inc. et al., the
City of Rochester sued multiple parties after a water tower that it had built
in 1985 sprung a leak. New Hampshire has adopted the doctrine of Nullum
Tempus, which means that statutes of limitations do not apply against the
State. The question for this case was whether cities and towns are immune
from statutes of limitation. Preti Flaherty attorneys Ken Rubinstein and
Nathan Fennessy represented an ENR 50 Contractor who was named as a defendant
in the litigation.
Although the NH Supreme Court has previously held that Nullum
Tempus applies to claims brought by the State, the Superior Court soundly
criticized the doctrine, and refused to allow municipalities to exercise the
same rights. This decision should help to limit the scope of liability
for design professionals, contractors and subcontractors working on municipal
projects, by allowing the statute of limitations to establish an outside date
within which claims can be presented.
Maine Legislature Considers a Bill that Would Limit Indemnification Provisions in Construction Contracts
Monday, April 6, 2015
The Maine legislature is considering a bill that, if passed,
would have a significant impact on Maine contractors and subcontractors. LD-587 would make void and unenforceable any
provision in a construction contract requiring the parties or their sureties or
insurers to indemnify a promisee against liability arising from the negligence
or willful misconduct of the promisee. The
bill has been referred to the Committee on Labor, Commerce, Research and
Economic Development.
If passed,
neither contractors nor subcontractors could be held liable for the actions of
other parties to their contracts. While
there are currently some limits to what passes as an acceptable indemnity
agreement in Maine, this law would significantly alter the risks of liability
in many construction contracts, since owners frequently contract for broad
indemnity agreements with their contractors.
The bill
was introduced by Assistant Senate Majority Leader, Senator Andre Cushing
(R-Hampden) at the request of the Associated Builders and Contractors of
Maine. While it is somewhat unusual for
ABC Maine to support a bill limiting contractors’ rights to contract for
indemnity from their subcontractors, ABC Maine states that it supports this bill
because it holds parties responsible for their own actions, regardless of their
leverage in contract negotiations.
A public
hearing on the bill was held on March 17, 2015.
In oral testimony and written submissions, representatives of Maine
contractors and subcontractors explained that they support this bill because
they are frequently compelled to submit to onerous contract requirements given
Maine’s competitive construction industry. Opponents argued that the bill is vague,
unnecessary, shifts risk from contractors to owners, and puts undue constraints
on the free market. They further argued
that contractors should assume responsibility for workplace injuries since they
should have primary control over the worksite and procure insurance for
accepting that responsibility.
The bill
currently remains pending in committee. Similar
bills have been brought before the Maine legislature several times in the past
20 years and have failed to pass.
Labels:
ABC Maine,
Associated Builders and Contractors of Maine,
bill,
construction law,
contractors,
contractors' rights,
LD-587,
Maine,
Maine Legislature,
Senator Andre Cushing
NH Supreme Court Limits Applicability of Consumer Protection Act to Construction Defect Cases
Wednesday, April 1, 2015
The New Hampshire Supreme Court confirmed in Murray v. McNamara,
No. 2013-630 (N.H. March 20, 2015) that contractors are exempt from liability
under New Hampshire’s Consumer Protection Act (RSA 358-A) for transactions
occurring more than three years prior to the plaintiff learning of the alleged
violation of the statute (though
they may still have liability under other causes of action). This issue arose in the context of a construct defect claim
based on defendants’ purported breach of the implied warranty of workmanlike
quality. The defendants, owners of a construction business, constructed
the house for the original owner in 2004. Four years later, the
plaintiffs purchased the home. After living in the house for several months,
the plaintiffs discovered mold in in the house that was so widespread it forced them to vacate the
property while they attempted to remedy the problem.
The Defendants argued that the transaction was exempt from
liability under the CPA because it was brought more than three years after
construction was completed. RSA 358-A:3, IV-a provides that
“[t]ransactions entered into more than 3 years prior to the time the plaintiff
knew, or reasonably should have known, of the conduct alleged to be in
violation of [the CPA]” are exempt from the CPA.” The federal courts in
New Hampshire had interpreted this provision as being different from a statute
of limitation because it “focuses on the plaintiff’s knowledge of the
defendant’s wrongful conduct” to determine whether a transaction is exempt from
the CPA rather than “the plaintiff’s knowledge of his injury and its [causal]
relationship to the defendants’ conduct.” The NH Supreme Court had not
yet considered the issue since the provision was amended in 1996, but concluded
in Murray that it agreed with the federal court’s interpretation finding
that
To determine whether a claim is
exempt from the CPA, we look back from the time that the plaintiffs “knew or
reasonably should have known” of the alleged violation. If the transaction at
issue occurred more than three years before that time, then it is exempt. The
person claiming the exemption bears the burden of proving that the transaction
is exempt. See RSA 358-A:3, V (2009).
The Court found there was no dispute that the transaction at issue
- defendants’ alleged construction of the house with latent structural defects
- was completed in 2004 and that plaintiffs purchased the home four years
later. Because the allegedly wrongful transaction occurred more than
three years before the plaintiffs “knew or reasonably should have known” of it,
the construction of the house was an exempt transaction pursuant to RSA
358-A:3, IV-a. The Court therefore reversed the trial court’s ruling on
the CPA claim, but
left in place the jury award on the warranty claim against the contractor.
Labels:
construction,
construction law,
Murray v. McNamara,
New Hampshire Consumer Protection Act,
New Hampshire Supreme Court
Equitable Adjustment Not Available to Remedy “Wholly Artificial” Bids
Monday, March 30, 2015
The
Massachusetts Appeals Court has declined to award an equitable adjustment to a
contractor who bid $0.01 to excavate a cubic yard of rock from a project site. See Celco Construction Corp. v. Town of Avon,
87 Mass. App. Ct. 132 (March 2, 2014).
The contractor constructed its bid based on its belief that the amount
of rock on the site would be considerably less than the unverified estimate
indicated in the contract bid documents, so that its low unit price would give
it a competitive advantage when compared to the other bidders who assigned a
unit price to rock removal that more closely approximated the actual cost. When the amount of rock turned out to be 2524
cubic yards, and not 1000 cubic yards, as estimated, the contractor sought an
equitable adjustment. Initially, the
contractor sought to increase the contract from $0.01 per cubic yard to $220
per cubic yard, and eventually dropped the request to $190 per cubic yard.
Massachusetts General Laws, c. 30, § 39N, which governs equitable adjustments in public construction contracts, provides that in all public construction contracts (such as the one at issue here), there must be a provision allowing either party to request an equitable adjustment in the contract price “if, during the progress of the work, the contractor or the awarding authority discovers that the actual subsurface or latent physical conditions encountered at the site differ substantially or materially from those shown on the plans or indicated in the contract documents.” The contractor argued that the approximately 1500 more cubic yards of rock presented an appropriate occasion for an equitable adjustment to compensate it for the increased costs it incurred to remove the additional rock.
The Court disagreed, noting that there was nothing to suggest that the nature of the rock itself, and the means to remove it, differ in any way from what was anticipated in the contract. The Court decided that in a contract in which the contract price is comprised of the aggregate of line items for various elements of the work, which in turn are based on unit prices for the quantities involved in each line item, no equitable adjustment is warranted by reason of a variation in the estimated quantities, standing alone, as compared to a deviation in the condition or character of the physical condition. The Court confirmed that an equitable adjustment is required only when the contractor encounters a material difference in the “actual subsurface or latent physical conditions . . . at the site . . . of such a nature as to cause an increase or decrease in the cost . . . of the work.”
The Court included in its opinion advice for all contractors in bidding on public construction jobs (and on all jobs in general): “Had [the contractor] in its bid assigned to rock removal a unit price reasonably approximating its estimated cost for such removal, instead of assigning the wholly artificial and unrealistic value of one penny, it would be in no need of adjustment to the contract price. Put another way, [the equitable adjustment statute] is designed to protect contractors from unknown and unforeseen subsurface conditions, not from the consequences of their decisions to bid a unit price for the performance of work that is wholly unrelated to their anticipated cost to perform the work. In such circumstances, it defies logic to invoke ‘equity’ as a basis for adjustment to the contract price.”
Massachusetts General Laws, c. 30, § 39N, which governs equitable adjustments in public construction contracts, provides that in all public construction contracts (such as the one at issue here), there must be a provision allowing either party to request an equitable adjustment in the contract price “if, during the progress of the work, the contractor or the awarding authority discovers that the actual subsurface or latent physical conditions encountered at the site differ substantially or materially from those shown on the plans or indicated in the contract documents.” The contractor argued that the approximately 1500 more cubic yards of rock presented an appropriate occasion for an equitable adjustment to compensate it for the increased costs it incurred to remove the additional rock.
The Court disagreed, noting that there was nothing to suggest that the nature of the rock itself, and the means to remove it, differ in any way from what was anticipated in the contract. The Court decided that in a contract in which the contract price is comprised of the aggregate of line items for various elements of the work, which in turn are based on unit prices for the quantities involved in each line item, no equitable adjustment is warranted by reason of a variation in the estimated quantities, standing alone, as compared to a deviation in the condition or character of the physical condition. The Court confirmed that an equitable adjustment is required only when the contractor encounters a material difference in the “actual subsurface or latent physical conditions . . . at the site . . . of such a nature as to cause an increase or decrease in the cost . . . of the work.”
The Court included in its opinion advice for all contractors in bidding on public construction jobs (and on all jobs in general): “Had [the contractor] in its bid assigned to rock removal a unit price reasonably approximating its estimated cost for such removal, instead of assigning the wholly artificial and unrealistic value of one penny, it would be in no need of adjustment to the contract price. Put another way, [the equitable adjustment statute] is designed to protect contractors from unknown and unforeseen subsurface conditions, not from the consequences of their decisions to bid a unit price for the performance of work that is wholly unrelated to their anticipated cost to perform the work. In such circumstances, it defies logic to invoke ‘equity’ as a basis for adjustment to the contract price.”
An Alternative to Bid Protests – California Court Allows Second Low Bidder to Sue Low Bidder Directly
Friday, March 13, 2015
In Roy Allan Slurry Seal, et al. v American Asphalt
South, Inc. (2/20/2015), the
court held that if a low bidder is only able to secure the bid by paying its
workers less than the required prevailing wage, then second low bidder is entitled
to bring a direct law suit against the low bidder.
The usual course of action in a case such as
this would be for the second low bidder to file a bid-protest with the awarding
authority, or to challenge any subsequent bid based upon such conduct.
However, this carries strong implications as the same principle could allow a
second low bidder to sue the low bidder directly any time that it can show that
that a low bidder knowingly used cut corners to secure the bid. For
example, contractors who commit wage-hour violations may be subject to
challenge from the second low bidder, contending that they carried a lower
labor number than appropriate in their bid. If the second low bidder can
show that the difference allowed the winning contractor to secure the bid, the
contractor may be subject to significant liabilities.
The broader facts are as
follows. From 2009 to 2012, American Asphalt outbid Roy Allan Slurry Seal
and Doug Martin Contractor on 23 public works projects valued at more than
$14.6 million. The disappointed
contractors, Allan and Martin, later jointly sued
American Asphalt, contending that they would have been the low bidders on those
projects if American Asphalt’s bid had included labor costs based on the
statutorily required prevailing wage. American moved to dismiss
the claims, arguing that that Allan and Martin did not have the required
existing relationship and reasonable probability of being awarded the contracts
to show intentional interference with prospective economic advantage.
After various conflicting lower court rulings on the issue, the matter was
eventually presented to the California Court of Appeals, which denied the motions, stating:
The second-place
bidder on a public works contract [may] state a cause of action for intentional
interference with prospective economic advantage against the winning bidder if
the winner was only able to obtain lowest bidder status by illegally paying its
workers less than the prevailing wage... if the plaintiff alleges it was the
second lowest bidder and therefore would have otherwise been awarded the
contract, because that fact gives rise to a relationship with the public agency
that made plaintiff’s award of the contract reasonably probable.
Arbitration Waiver Violates Chapter 93A
Monday, March 2, 2015
A Massachusetts Superior Court Judge has held that a contractor’s failure to register with the Commonwealth under Mass. Gen. Laws. Chapter 142A constitutes an injury under Mass. Gen. Laws c. 93A (the Massachusetts Consumer Protection Statute). See Groleau v. Russo-Gariele, Norfolk Superior Court, Civil Action No. 2012-01818. Chapter 142A regulates the home improvement contracting industry and allows a homeowner to submit disputes under the Home Improvement Contractor Arbitration Program (“HICARB”).
The homeowner hired the contractor to perform work on her home. The contractor told the homeowner she needed to sign an “Affidavit/Home Improvement Contractor Law Supplement to Permit Application” in order to get a building permit. The affidavit identified the contractor as a “Home Improvement Contractor” and contained language at the bottom indicating that homeowners dealing with unregistered contractors did not have access to HICARB. At the time, the contractor was not registered with the Commonwealth. He did not inform the homeowner of this.
Prior to completion of the project, the contractor stopped working on the property and sued the homeowner for unpaid amounts. The homeowner counterclaimed alleging breach of contract, as well as violations of Chapters 142A and 93A. At the conclusion of the jury-waived trial, the judge found that the homeowner owed the contractor $1,988. However, he also found that the contractor violated Chapter 142A by operating without a certificate of registration. The judge found that the homeowner could show actual damage stemming from the contractor’s failure to register because she lost the ability to arbitrate the dispute, which may have resulted in significant additional attorneys’ fees.
In finding that the homeowner sustained “injury,” the judge found that the contractor abandoned the project without justification, given that he was not owed substantial funds, and had accepted payment for work he had not performed. The judge held that the abandonment caused additional costs attributable to the completion of work within the scope of the contract and deprivation of occupancy of the property that the homeowner otherwise would have enjoyed. The judge dismissed the contractor’s argument that signing the affidavit waived the plaintiff’s right to arbitrate, noting that Chapter 142A makes it unlawful for any agreement for residential contracting services to contain a provision that would waive any rights conveyed to the owner under that chapter. Additionally, the judge held that the affidavit did not actually waive the owner’s statutory rights by its terms. The affidavit also does not waive Chapter 142A rights in a clear and conspicuous way as would be expected in a consumer transaction in which a business owner claims a consumer has waived consumer protection rights. The judge noted that the information in the affidavit referencing unregistered contractors was merely a “notice” and is not suggestive of a waiver of statutory rights is signed by the homeowner.
The judge entered judgment for the homeowner on her Chapter 93A claim, which allows her to submit a motion for the contractor to pay her legal fees and costs. This case shows how the courts will work to invalidate written agreements that require a consumer to give up a statutorily protected consumer right and will also invalidate agreements that include waivers which are not “clear and conspicuous.”
The homeowner hired the contractor to perform work on her home. The contractor told the homeowner she needed to sign an “Affidavit/Home Improvement Contractor Law Supplement to Permit Application” in order to get a building permit. The affidavit identified the contractor as a “Home Improvement Contractor” and contained language at the bottom indicating that homeowners dealing with unregistered contractors did not have access to HICARB. At the time, the contractor was not registered with the Commonwealth. He did not inform the homeowner of this.
Prior to completion of the project, the contractor stopped working on the property and sued the homeowner for unpaid amounts. The homeowner counterclaimed alleging breach of contract, as well as violations of Chapters 142A and 93A. At the conclusion of the jury-waived trial, the judge found that the homeowner owed the contractor $1,988. However, he also found that the contractor violated Chapter 142A by operating without a certificate of registration. The judge found that the homeowner could show actual damage stemming from the contractor’s failure to register because she lost the ability to arbitrate the dispute, which may have resulted in significant additional attorneys’ fees.
In finding that the homeowner sustained “injury,” the judge found that the contractor abandoned the project without justification, given that he was not owed substantial funds, and had accepted payment for work he had not performed. The judge held that the abandonment caused additional costs attributable to the completion of work within the scope of the contract and deprivation of occupancy of the property that the homeowner otherwise would have enjoyed. The judge dismissed the contractor’s argument that signing the affidavit waived the plaintiff’s right to arbitrate, noting that Chapter 142A makes it unlawful for any agreement for residential contracting services to contain a provision that would waive any rights conveyed to the owner under that chapter. Additionally, the judge held that the affidavit did not actually waive the owner’s statutory rights by its terms. The affidavit also does not waive Chapter 142A rights in a clear and conspicuous way as would be expected in a consumer transaction in which a business owner claims a consumer has waived consumer protection rights. The judge noted that the information in the affidavit referencing unregistered contractors was merely a “notice” and is not suggestive of a waiver of statutory rights is signed by the homeowner.
The judge entered judgment for the homeowner on her Chapter 93A claim, which allows her to submit a motion for the contractor to pay her legal fees and costs. This case shows how the courts will work to invalidate written agreements that require a consumer to give up a statutorily protected consumer right and will also invalidate agreements that include waivers which are not “clear and conspicuous.”
Recent Supreme Court Decisions Strengthen NH Statute of Repose
Friday, February 27, 2015
The New Hampshire Supreme Court has issued two decisions in the past two weeks that bolster the strength of New Hampshire’s 8 year statute of repose.
Statute of Repose not Tolled During Period Where Contractor also Owned Property
In Ingram v. Drouin (February 12, 2015), the Plaintiffs argued that New Hampshire’s 8-year statute of repose did not bar their claims because the defendants not only built the home, but also once owned and possessed it. Therefore, the Plaintiffs argued, the defendants are not entitled to the protection of the statute of repose. The New Hampshire Supreme Court disagreed, stating, “We agree with the majority of courts addressing the issue that, when a builder-owner is sued for his construction-related activities, the statute of repose applies. To interpret the statute of repose otherwise would be contrary to the legislature's intent in enacting it— which was to protect the building industry.”
High Court Affirms Constitutionality of Statute of Repose
In Jillian Lennartz v. Oak Point Associates, P.A. & a. (February 20, 2015), the Plaintiff missed the statute of repose deadline by 3 months. The Plaintiff then argued that New Hampshire’s 8 year statute of repose was unconstitutional. The Plaintiff raised a variety of arguments, which the New Hampshire Supreme Court soundly rejected. Ultimately, the Court disagreed, noted that it had previously rejected nearly identical arguments in Winnisquam Reg. Sch. Dist. v. Levine, 152 N.H. 537 (2005). The Court went on to state, “The plaintiff concedes that the purpose of RSA 508:4-b, I, in preventing potentially infinite liability in the building industry is an important government objective, and we see no reason to modify our prior conclusion...”
Statute of Repose not Tolled During Period Where Contractor also Owned Property
In Ingram v. Drouin (February 12, 2015), the Plaintiffs argued that New Hampshire’s 8-year statute of repose did not bar their claims because the defendants not only built the home, but also once owned and possessed it. Therefore, the Plaintiffs argued, the defendants are not entitled to the protection of the statute of repose. The New Hampshire Supreme Court disagreed, stating, “We agree with the majority of courts addressing the issue that, when a builder-owner is sued for his construction-related activities, the statute of repose applies. To interpret the statute of repose otherwise would be contrary to the legislature's intent in enacting it— which was to protect the building industry.”
High Court Affirms Constitutionality of Statute of Repose
In Jillian Lennartz v. Oak Point Associates, P.A. & a. (February 20, 2015), the Plaintiff missed the statute of repose deadline by 3 months. The Plaintiff then argued that New Hampshire’s 8 year statute of repose was unconstitutional. The Plaintiff raised a variety of arguments, which the New Hampshire Supreme Court soundly rejected. Ultimately, the Court disagreed, noted that it had previously rejected nearly identical arguments in Winnisquam Reg. Sch. Dist. v. Levine, 152 N.H. 537 (2005). The Court went on to state, “The plaintiff concedes that the purpose of RSA 508:4-b, I, in preventing potentially infinite liability in the building industry is an important government objective, and we see no reason to modify our prior conclusion...”
New Hampshire Supreme Court Interprets "Your Work" Exclusion in CGL Policy
Wednesday, January 14, 2015
The NH Supreme Court issued an important ruling yesterday, clarifying the “Your Work” exclusion under a standard Commercial
General Liability (CGL) Policy. See Cogswell Farm Condominium Association v. Tower Group,
Inc.
Executive Summary
Executive Summary
Under the Court's ruling, the “Your Work”
exclusion in the standard CGL policy only bars coverage for property damage
to the defectively constructed portions of a contractor’s work. It
will not preclude claims for damage to the non-defective parts of the work. In
other words, if a contractor’s defective work causes damage to other
non-defectively built portions of the project, the contractor cannot recover its
costs for repairing the defectively performed work, but can claim coverage for
the damage to the non-defective work.
Discussion
In Cogswell, a
contractor’s defective work (a leaky water barrier) caused water damage to
several condo units that the contractor had properly constructed. The property
owner sued the contractor and sought to recover under the contractor’s CGL
policy. The contractor’s insurance carrier, however, denied coverage based upon
the policy's “Your Work” exclusion in policy. This exclusion precludes coverage
for property damage for “[t]hat particular part of any property that must be
restored, repaired or replaced because ‘your work’ was incorrectly performed on
it.” The carrier argued that this clause precluded any claim for damage to the
contractor’s own work.
The trial court found in favor of
the insurer, but the New Hampshire Supreme Court overturned the decision,
holding that while the insurer’s interpretation was reasonable, the policy could
also be read in a more limited fashion, only barring claims for the cost of
repairing the defective work. The court held that since either interpretation
was reasonable, the policy was ambiguous, and the ambiguity must be resolved in
favor of the insured. Accordingly, the court concluded by stating that:
[The “Your Work”
exclusion] bars coverage for property damage to the defectively constructed
portions of the condominium units...however, [the exclusion] does not bar
coverage for damage to those portions of the units that were not defectively
constructed by [the Contractor] but were damaged as a result of the defective
work.
Important Note
Courts nationwide have disagreed
sharply on this issue. Accordingly, while Cogswell is good law in New
Hampshire, courts in other jurisdictions may not follow the same rationale, and
contractors should check the law in their specific jurisdiction when dealing
with this issue.
Who is Entitled to Receive a “Refund” in NH of Impact Fees May Surprise You
Tuesday, January 6, 2015
We usually think that the word “refund,” refers to money being returned to the person who paid it. The NH Supreme Court, in the recent case of K.L.N. Construction Company, Inc. v. Town of Pelham, 2013-0374, turned this notion on its head in concluding that a “refund” of impact fees could be paid to current property owners that never paid the impact fee in the first place.
The Town of Pelham adopted an impact fee ordinance in 1999 (pursuant to RSA 674:16 and RSA 674:21, V) assessing fees on new development in order to pay for capital improvements. The ordinance provided that, if the Town had not spent or otherwise encumbered the impact fees within six years, “[t]he current owners of property on which impact fees have been paid may apply for a full or partial refund of such fees, together with any accrued interest.” (emphasis added). Subsequent to the enactment of the ordinance, the Town required certain residential real estate developers to pay impact fees to the Town. After paying the fees, the developers sold the properties to individual homeowners.
Certain of these residential developers sought the refund of impact fees that they had paid more than six years earlier. The Town argued that because these developers no longer owned the properties which had been developed, they lacked standing to seek a refund of the impact fees. The trial court agreed with the Town finding that the statute did not prevent municipalities from choosing to direct refunds to the current property owners. The developers then appealed and the NH Supreme Court affirmed.
The NH Supreme Court reached its conclusion primarily by considering how the term “refund” was used in connection with unused exactions in another statute (RSA 674:21, V(j)). Exactions are fees charged to a developer for off-site improvements needed for the occupancy of a development. When an exaction is predicated upon a municipality paying a portion of the improvement’s cost, and the municipality fails to appropriate its share of the cost within six years, the statute provides that “a refund of any collected exaction shall be made to the payor or payor’s successor in interest.” The residential developers argued a similar interpretation should apply to impact fees. The Court concluded, however, that the absence of the “payor or payor’s successor in interest” language in the impact fee statute, which was enacted a decade before the exaction statute, indicated that the legislature did not intend the two sections to have identical meanings. The Court then concluded that the Legislature must have intended the potential recipients of impact fee refunds to be broader than the residential developers who paid them or their successor’s in interest. Thus, the Town properly interpreted the impact fee statute in making its decision to refund such fees to current property owners rather than the residential developers who paid them.
The Town of Pelham adopted an impact fee ordinance in 1999 (pursuant to RSA 674:16 and RSA 674:21, V) assessing fees on new development in order to pay for capital improvements. The ordinance provided that, if the Town had not spent or otherwise encumbered the impact fees within six years, “[t]he current owners of property on which impact fees have been paid may apply for a full or partial refund of such fees, together with any accrued interest.” (emphasis added). Subsequent to the enactment of the ordinance, the Town required certain residential real estate developers to pay impact fees to the Town. After paying the fees, the developers sold the properties to individual homeowners.
Certain of these residential developers sought the refund of impact fees that they had paid more than six years earlier. The Town argued that because these developers no longer owned the properties which had been developed, they lacked standing to seek a refund of the impact fees. The trial court agreed with the Town finding that the statute did not prevent municipalities from choosing to direct refunds to the current property owners. The developers then appealed and the NH Supreme Court affirmed.
The NH Supreme Court reached its conclusion primarily by considering how the term “refund” was used in connection with unused exactions in another statute (RSA 674:21, V(j)). Exactions are fees charged to a developer for off-site improvements needed for the occupancy of a development. When an exaction is predicated upon a municipality paying a portion of the improvement’s cost, and the municipality fails to appropriate its share of the cost within six years, the statute provides that “a refund of any collected exaction shall be made to the payor or payor’s successor in interest.” The residential developers argued a similar interpretation should apply to impact fees. The Court concluded, however, that the absence of the “payor or payor’s successor in interest” language in the impact fee statute, which was enacted a decade before the exaction statute, indicated that the legislature did not intend the two sections to have identical meanings. The Court then concluded that the Legislature must have intended the potential recipients of impact fee refunds to be broader than the residential developers who paid them or their successor’s in interest. Thus, the Town properly interpreted the impact fee statute in making its decision to refund such fees to current property owners rather than the residential developers who paid them.
Labels:
exaction fees,
impact fee ordinance,
impact fee refunds,
KLN Construction Company,
NH Supreme Court,
residential real estate developer fees,
successor in interest,
Town of Pelham
Subscribe to:
Posts (Atom)